- quarrying white stone for the dripstones on the enclosing wall between the western tower and the residential tower and for the ribs of the Gothic vaulting;
- covering the entrance tower with a provisional roof of bitumen-impregnated cardboard;
- covering the truss of the entrance tower and the western tower with oak floorboards;
- restoring the floor covering of the 1st floor of the 2nd tower;
- restoring the Gothic vaulting in the residential tower;
- flooring the enclosing wall with flat white stones or Spanish bricks on top of the entrance tower and the ramparts;
- urgently completing the reinforcement of the western tower;
- installing three windows with shutters, a door and a window with old stained glass inserts on the 2nd floor of the entrance tower, to create a rain-proof and wind-proof reception area.
- repairing the entrance tower.